View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7157
Project Title: Replace Perimeter Security Fence (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: BJW
Description: Remove, replace and upgrade existing perimeter security fence.
Location: Indian Springs
DI_Location_2: 0
Project Description: Project scope includes design from the design development through construction documents phases and construction to upgrade and square-off the existing perimeter security fencing at the Southern Desert Correctional Center (SDCC). Scope of work will include new perimeter fencing, new razor wire including razor wire between inside and outside perimeter fence, and a new perimeter roadway. Design through the schematic design phase is planned separately with CIP Application 7075.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove Perimeter Security Fence (2,500 lf @ $28/lf) 70,000
2 Relocate Propane Gas Tanks & Concrete Pad 50,000
3 Relocate Switchgear & Transformer 100,000
4 Construct Perimeter Roadway 630,000
5 Install High Mast Lights (5 ea @ $90,000/ea) 450,000
6 Upgrade Existing Perimeter Fence (1,300 lf @ $130/lf) 169,000
7 Install Perimeter Security Fence (12,200 lf @ $235/lf) 2,867,000
8
9
10
11
12
13
14
15
16
Total 4,336,000