View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7151
Project Title: Roofing Replacement, Comfort 1 & 2 Big Ben
Agency: SPWD
Division: SPWD
Department: Admin
Project Manager: MHF
Description: This project would provide for a single ply roofing system.
Location: Other
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (650 sf @ $1/sf) 650
2 Membrane Installation (650 sf @ $10.5/sf) 6,825
3 Polyisocyanurate Insulation (650 sf @ $2/sf) 1,300
4 Metal Coping Cap (100 lf @ $15/lf) 1,500
5 Misc Components (650 sf @ $1/sf) 650
6
7
8
9
10
11
12
13
14
15
16
Total 10,925