View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7145
Project Title: Roofing Replacement, Mormon Fort, Administration
Agency: CNR
Division: CNR
Department: CNR
Project Manager: MHF
Description: This project would provide for a single ply roofing system
Location: Las Vegas
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (9,000 sf @ $1/sf) 9,000
2 Roofing - Membrane (9,000 sf @ $10.5/sf) 94,500
3 Misc Components (9,000 sf @ $1/sf) 9,000
4 Metal Coping Cap (300 lf @ $20/lf) 6,000
5 Walk Pads (300 lf @ $2/lf) 600
6
7
8
9
10
11
12
13
14
15
16
Total 119,100