View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7141
Project Title: Security Cameras (Warm Springs Correctional Center)
Agency: WSCC
Division: WSCC
Department: NDOC
Project Manager: CAD
Description: Install cameras, workstations and digital storage .
Location: Carson City
DI_Location_2: 0
Project Description: This project would design and construct video monitoring and recording equipment in every common inmate area and visitor area in Warm Springs Correctional Center. It would also include cameras in housing units.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Fixed Cameras (140 ea @ $4,000/ea) 560,000
2 Pan-Tilt-Zoom Cameras (2 ea @ $5,000/ea) 10,000
3 Enhanced Digital Storage 150,000
4 Monitoring Workstations (15 ea @ $2,500/ea) 37,500
5 Trenching, Conduit, Conductor Install (4,000 lf @ $50/lf) 200,000
6
7
8
9
10
11
12
13
14
15
16
Total 957,500