Description: Construct a bus parking area with access next to the existing visitors center parking lot.
Location: Pioche
DI_Location_2: 0
Project Description: The project will adjust the existing parking lot and sidewalks, and establish a new bus 11,000 sf parking area and access route to the west of the existing parking lot.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Selective Demolition 5,000
2 Clearing & Grubbing (11,000 sf @ $1/sf) 11,000
3 Overexcavate & Haul (800 cy @ $25/cy) 20,000
4 Import & Compact (800 cy @ $28/cy) 22,400
5 Grading (11,000 sf @ $.75/sf) 8,250
6 AC Paving (11,000 sf @ $5/sf) 55,000
7 Curb & Gutter (260 lf @ $20/lf) 5,200
8 Sidewalk (2,000 sf @ $12/sf) 24,000
9 Striping 2,500
10 Lighting (5 ea @ $9,000/ea) 45,000
11
12
13
14
15
16
Total 198,350