Application ID: 7138
Project Title: New Paving at the Fire Wave and White Domes Parking Areas (Valley of Fire)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: MJM
Description: Expand the parking areas at the Fire Wave and White Domes areas in the park.
Location: Overton
DI_Location_2: 0
Project Description: This project will increase, pave and stripe the existing gravel Fire Wave parking lot to accommodate 50 vehicles. It will also widen the existing White Domes Terminus loop to increase parking from 19 stalls to 35 and adjusting striping/layout. Curb & gutt

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clear & Grub, Fire Wave (6,800 sf @ $1/sf) 6,800
2 Excavate & Haul, Fire Wave (500 cy @ $40/cy) 20,000
3 Import Fill & Compact, F.W (500 cy @ $30/cy) 15,000
4 Finish Grading, F.W (17,000 sf @ $1/sf) 17,000
5 AC 3" O/ 6", Fire Wave (17,000 sf @ $3/sf) 51,000
6 Parking Striping, Fire Wave (50 ea @ $12/ea) 600
7 Clear & Grub, White Dome (4,000 sf @ $1/sf) 4,000
8 Excavate & Haul, White Dome (200 cy @ $40/cy) 8,000
9 Import Fill & Compact, W.D (200 cy @ $30/cy) 6,000
10 Drainage, Curb & Gutter/V-Gutter, W.D. 20,000
11 Finish Grading, White Dome (4,000 sf @ $1/sf) 4,000
12 AC 3" O/ 6", White Dome (4,000 sf @ $3/sf) 12,000
13 Seal Existing/ Ac, W.D (30,000 sf @ $.6/sf) 18,000
14 Parking Striping, White Dome (19 ea @ $12/ea) 228
15 Signage Reconfigure, Both Areas 2,000
16
Total 184,628