View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7137
Project Title: Site Rehabilitation (Cathedral Gorge State Park)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: MJM
Description: Seal existing pavements, and construct AC pavement area within the maintenance yard.
Location: Pioche
DI_Location_2: 0
Project Description: This project will rehabilitate the existing asphalt paving for the 1.6 mile access road to and through the park. It will also correct the drainage and provide new asphalt paving in the maintenance area of the park.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Seal Access Road (190,000 sf @ $.45/sf) 85,500
2 Overexcavate & Off-Haul (1,000 cy @ $20/cy) 20,000
3 Import Fill (1,000 cy @ $25/cy) 25,000
4 Rough Grading, Maintenance Area (26,000 sf @ $.15/sf) 3,900
5 Fine Grading, Maintenance Area (26,000 sf @ $.35/sf) 9,100
6 Drainage Correction, Maintenance Area 35,000
7 3" Paving on 6" Base, Maint Area (26,000 sf @ $3/sf) 78,000
8 Crack Seal, Visitors Center (10,000 sf @ $.15/sf) 1,500
9 Type 2 Slurry, Visitors Center (10,000 sf @ $.45/sf) 4,500
10
11
12
13
14
15
16
Total 262,500