View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7134
Project Title: Vehicle and Material Storage Building (Rye Patch State Park)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: MJM
Description: Design and construct a 2,200 sf vehicle and material storage building.
Location: Lovelock
DI_Location_2: 0
Project Description: This project would provide a 2,200 square foot, prefabricated metal storage and shop building. Due to the higher summer temperatures, the facility will need air conditioning in addition to heating. State Fire Marshal's Office requires facility to be fully sprinklered which includes a new water Tank.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Sitework 35,000
2 Concrete (1,600 sf @ $12/sf) 19,200
3 Pre-Fab Structure (2,200 sf @ $110/sf) 242,000
4 Interior Finishes (2,200 sf @ $23/sf) 50,600
5 Electrical (2,200 sf @ $13/sf) 28,600
6.
7.
8.
9
10
11
12
13
14
15
16
Total 375,400