View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7132a
Project Title: Vehicle and Material Storage Building (Wildhorse State Park)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: MJM
Description: Design and construct a 2,500 sf shop, vehicle and material storage building.
Location: Elko
DI_Location_2: 0
Project Description: This project would provide an 2,500 square foot, prefabricated metal storage and shop building. The project also includes approximately 120 additional linear feet of fenced yard to secure the area.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Sitework 35,000
2 Concrete (1,800 sf @ $10/sf) 18,000
3 Pre-Fab Structure (2,500 sf @ $110/sf) 275,000
4 Interior Finishes (2,500 sf @ $23/sf) 57,500
5 Electrical (2,500 sf @ $13/sf) 32,500
6 Fencing (125 lf @ $30/lf) 3,750
7.
8.
9.
10.
11.
12
13
14
15
16
Total 421,750