View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7130
Project Title: Replace High Mast Lighting ( LCC NNCC WSCC HDSP ESP)
Agency: NDOC
Division: NDOC
Department: NDOC
Project Manager: CAD
Description: Replace high mast lighting with LED lighting for higher efficiency
Location: Various
DI_Location_2: 0
Project Description: This project will replace the high mast lighting fixtures with LED lighting fixtures. It will also replace the cables and operators for these poles, as they are worn out, and becoming a liability for staff and inmates. The power usage will decrease from approximately 1100 watts per fixture to approximately 400 watts per fixture.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace High Mast Lighting with LED-LCC (130 ea @ $3,000/ea) 390,000
2 Replace Cables & Operators LCC (13 ea @ $8,000/ea) 104,000
3 Replace High Mast Lighting with LED-NNCC (190 ea @ $3,000/ea) 570,000
4 Replace Cables & Operators NNCC (19 ea @ $8,000/ea) 152,000
5 Replace High Mast Lighting with LED-WSCC (80 ea @ $3,000/ea) 240,000
6 Replace Cables & Operators WSCC (7 ea @ $8,000/ea) 56,000
7 Replace High Mast Lighting with LED-HDSP (310 ea @ $3,000/ea) 930,000
8 Replace Cables & Operators HDSP (31 ea @ $8,000/ea) 248,000
9 Replace High Mast Lighting with LED-ESP (170 ea @ $3,000/ea) 510,000
10
11
12
13
14
15
16
Total 3,200,000