Application ID: 7129
Project Title: Vehicle and Material Storage Building (Valley of Fire State Park)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: CSB
Description: Design and construct a 3,000 sf vehicle and material storage building.
Location: Overton
DI_Location_2: 0
Project Description: This project would provide a 3,000 square foot, prefabricated metal storage building. This building would provide storage space for vehicles, equipment and materials as needed. Due to the extreme summer temperatures, the facility will need power, lighting and an evaporative cooler in addition to heating.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clear & Grub (5,000 sf @ $.1/sf) 500
2 Site Earthwork (1,000 cy @ $25/cy) 25,000
3 Concrete Site Work (3,000 sf @ $15/sf) 45,000
4 Pre-Fabricated Metal Building (3,000 sf @ $80/sf) 240,000
5 Wet & Dry Utilities 15,000
6 Landscaping (3,000 sf @ $1/sf) 3,000
7
8
9
10
11
12
13
14
15
16
Total 328,500