Description: Design and construct a 2,300 sf vehicle and material storage building.
Location: Other
DI_Location_2: 0
Project Description: This project would provide a 2,300 square foot, prefabricated metal storage building with stucco wall finishes to match the other maintenance and residential buildings. This project would also include approximately 800 additional linear feet of fenced yard to secure the area.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clear & Grub 5,000
2 Concrete Site Work (1,600 sf @ $12/sf) 19,200
3 Utility Trenching (1,500 lf @ $50/lf) 75,000
4 Concrete Curb & Gutter (1,500 lf @ $20/lf) 30,000
5 Earthwork Finish Grading 32,000
6 Fencing (800 lf @ $25/lf) 20,000
7 Prefab Metal Bldg with Stucco Walls (2,300 sf @ $145/sf) 333,500
8
9
10
11
12
13
14
15
16
Total 514,700