View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7114
Project Title: Culinary Flooring Replacement (Lovelock Correctional Center)
Agency: LCC
Division: LCC
Department: NDOC
Project Manager: JJD
Description: Replace Culinary Flooring Including Walk-In Coolers/Freezers
Location: Lovelock
DI_Location_2: 0
Project Description: This scope of this project will design and construct quarry tile flooring and stainless steel coved base in the culinary areas (including coolers and freezers).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Cooler/Freezer - Demolition (2,500 sf @ $5/sf) 12,500
2 Cooler/Freezer - Quarry Tile Replacement (2,500 sf @ $35/sf) 87,500
3 Cooler/Freezer - Stainless Steel Coving (525 lf @ $75/lf) 39,375
4 Culinary Flooring - Equipment Move / Storage (5,100 sf @ $2/sf) 10,200
5 Culinary Flooring - Demolition (5,100 sf @ $5/sf) 25,500
6 Culinary Flooring - Quarry Tile Replacement (5,100 sf @ $35/sf) 178,500
7 Culinary Flooring - Stainless Steel Coving (650 lf @ $75/lf) 48,750
8 Temporary Kitchen - Rental 45,000
9 Temporary Kitchen - Utilities to Trailer 7,500
10 Temporary Kitchen - Propane Rental 60,000
11 Temporary Kitchen - Security Fencing (175 lf @ $100/lf) 17,500
12.
13.
14.
15.
16.
Total 532,325