View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7109
Project Title: Comfort Station (Fort Churchill State Park Campground)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: RMO
Description: Provide and install a new ADA compliant comfort station.
Location: Fallon
DI_Location_2: 0
Project Description: The scope of this project is to provide and install an ADA compliant, pre-manufactured, pre-cast concrete, comfort station at the Fort Churchill State Historic Park campground. The comfort station will contain four ADA compliant restrooms and two ADA compliant showers.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Comfort Station (800 sf @ $350/sf) 280,000
2 Solar PV Installation (2 kw) 38,000
3 Above Ground Septic Tank 54,000
4 Utility Connections / Site Work 22,000
5 Demolition 7,500
6
7
8
9
10
11
12
13
14
15
16
Total 401,500