Application ID: 7102
Project Title: Replace Finishes and Surveillance (High Desert State Prison -Infirmary/Intake Building)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: JJD
Description: Infirmary and suicide watch room flooring, painting, shower, and surveillance refurbishment.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of this project will refurbish vinyl composition tile (VCT) flooring, interior painting, and shower units at the High Desert State Prison infirmary/intake building. Not included in the scope are surveillance cameras for the three suicide watch cells, which was requested, but will require a "campus wide" monitoring solution.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Showers - Demolition (15 ea @ $2,500/ea) 37,500
2 Showers - Shower Inserts (15 ea @ $18,000/ea) 270,000
3 Flooring - Demolition (32,986 sf @ $3/sf) 98,958
4 Flooring (32,986 sf @ $6.5/sf) 214,409
5 Interior Painting 180,000
6 Surveillance Cameras (3 ea @ $7,500/ea) 22,500
7 Watch Room Surfaces 78,750
8
9
10
11
12
13
14
15
16
Total 902,117