Application ID: 7101
Project Title: Parking Lot Repair and New Paving (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: MJM
Description: Repair existing parking lot, add additional parking, pave West perimeter road and transport van parking area.
Location: Indian Springs
DI_Location_2: 0
Project Description: This project will provide grading and asphalt paving of the 16 foot wide by 3,500 foot long West perimeter road, a parking area for the transport vans, a new 60 space parking area, and repair and maintenance of the existing parking lot.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Pave Perimeter Road (60,000 sf @ $3/sf) 180,000
2 Pave Parking Area- 8 Oversize Stalls (3,000 sf @ $3/sf) 9,000
3 Striping (8 ea @ $12/ea) 96
4 Miscellaneous Patching (4,000 sf @ $6/sf) 24,000
5 Crack Seal (150,000 sf @ $.1/sf) 15,000
6 Type 2 Slurry (150,000 sf @ $.4/sf) 60,000
7 Striping 4,500
8 60 Space Parking Addition with Lighting 260,000
9
10
11
12
13
14
15
16
Total 552,596