Description: Safety rehabilitation of the stairs, foundations, guardrails and bridge, and installation of safety railings at overlook edge and at canyon walkways.
Location: Pioche
DI_Location_2: 0
Project Description: This project would provide life safety rehabilitation of the trailhead stair structures, foundations, guard rails and the bridge at the Miller Point Overlook at the Cathedral Gorge State Park. It also provides safety pipe railings at the edges of the upper and lower canyon visitor walking trails.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demo Cable Railings/Old Bridge/Wooden Steps in Canyon 50,000
2 Pipe Railings at Upper & Lower Canyon (5,000 lf @ $66/lf) 330,000
3 Steel Coating of Metal Stairs & Guardrails (2 ea @ $7,500/ea) 15,000
4 Rehab Metal Stair Foundations (2 ea @ $25,000/ea) 50,000
5 Bridge with Pipe Railings (100 sf @ $250/sf) 25,000
6
7
8
9
10
11
12
13
14
15
16
Total 470,000