View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7097
Project Title: Campground Improvements (Echo Canyon State Park)
Agency: Parks
Division: Parks
Department: CNR
Project Manager: CSB
Description: Remove & replace existing restroom building, provide ADA compliant restrooms and pull-through campsites.
Location: Pioche
DI_Location_2: 0
Project Description: The scope of this project is to remove an existing restroom building and replace it with a 600 sf restroom building consisting of three ADA compliant restroom stalls and one ADA shower stall. This project also includes a new ADA compliant campsite built

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Restroom Demolition 30,000
2 3 ADA Restrooms & 1 ADA Shower (600 sf @ $350/sf) 210,000
3 Construct Campsite by Restroom (200 sf @ $200/sf) 40,000
4 Retrofit Campsite #31 Across Street to ADA Site 30,000
5 Import Fill for ADA Campsites (3,200 cy @ $25/cy) 80,000
6
7
8
9
10
11
12
13
14
15
16
Total 390,000