Description: Provide roofing, flashing, sealing, painting, and mortar repointing of various structures at the Spring Mountain Ranch State Park.
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to complete design thru construction documents for building weatherization and exterior envelope protection for various historic buildings at the Spring Mountain Ranch State Park located 15 miles west of Las Vegas in the Red Rock Canyon National Conservation Area. Many of the buildings in Spring Mountain Ranch State Park are historic in nature and were built as early as 1870 and as recent as 2005. Rehabilitation and repair activities on these buildings requires State Historic Preservation Office (SHPO) review and approval. The rehabilitation and repair work includes selective demolition, pressure washing, cleaning of the building exteriors, scraping, sealing, priming, and repainting all siding, trim, and flashing at all of the buildings. Also included is re-roofing the old structures and rehabilitation of the wooden framing, while preserving the historic elements and their appearance, re-pointing of the mortar at various stone walls in the park, and adjusting the grades around the perimeter of the buildings where earth-to-wood contact exists, to create positive drainage away from the structures. The buildings included for rehabilitation and repair activities of work include: the Entrance Station; Wilson Residence/Sandstone Cabin; Historic Storage Building; Pump Control Station Building; Power Control Shed; Hay & Horse Barn; Dog Kennel; Historic Bunkhouse and Historic Blacksmith Shop (all of which are deteriorating rapidly).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Exterior Envelope Protection (4,382 sf @ $200/sf) 876,400
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 876,400