View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7091
Project Title: Connect Well 6 to Distribution System (HDSP)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: BJW
Description: Construct a well house and connect Well 6 to the water distribution system.
Location: Indian Springs
DI_Location_2: 0
Project Description: The project will connect Well 6 to the water distribution system at High Desert State Prison. The project scope includes finalization of construction documents, construction of a well house with associated equipment and, connection to the existing water distribution system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Site Grading (300 cy @ $25/cy) 7,500
2 Rip Rap Drainage Basin 3,000
3 Chain Link Fence (100 lf @ $50/lf) 5,000
4 Bollard (3 ea @ $800/ea) 2,400
5 Site Concrete 10,000
6 Well House Building 20,000
7 Well House Piping 30,000
8 Well House Electrical 25,000
9 Well House Mechanical 30,000
10 Chlorine Tank & Pump 2,500
11 Water System Control Upgrades 15,000
12 Site Water Distribution System Connections 50,000
13
14
15
16
Total 200,400