SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7090
Project Title: Upgrade Water Supply System (Various)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: BJW
Description: Construct water storage tanks at SDCC and ECC, construct a redundant water main at SDCC, recondition Tanks 1 & 2 at SDCC and, recondition tank at ECC.
Location: Various
DI_Location_2: 0
Project Description: At the Southern Desert Correctional Center (SDCC) - High Desert State Prison (HDSP) Complex this project will design and construct a second 18" water main to the existing water distribution system with valves and connections to provide a fully redundant w

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Construct 18" Water Line (13,000 lf @ $140/lf) 1,820,000
2 18" Water Line Valves & Connections 250,000
3 1,200,000 gallon Water Storage Tank 1,500,000
4 600,000 gallon Water Storage Tank 1,100,000
5 Update Electronic Controls 100,000
6 Recondition Tank #1 75,000
7 Recondition Tank #2 100,000
8 70,000 gallon Water Storage Tank at E.C.C 650,000
9 Recondition Water Storage Tank at E.C.C. 50,000
10
11
12
13
14
15
16
Total 5,645,000