Application ID: 7078
Project Title: HVAC Replacement (Casa Grande Transitional Housing Facility)
Agency: NDOC
Division: NDOC
Department: NDOC
Project Manager: BBM
Description: This project will replace 25 rooftop HVAC units at the Casa Grande facility.
Location: Las Vegas
DI_Location_2: 0
Project Description: This project will replace 25 rooftop HVAC units serving the administration building and residential buildings at the Casa Grande Transitional Housing Facility in Las Vegas.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Rooftop AC Unit (20 ton) 40,000
2 Rooftop AC Unit (12.5 ton) (6 ea @ $25,000/ea) 150,000
3 Rooftop AC Unit (10 ton) (5 ea @ $20,000/ea) 100,000
4 Rooftop AC Unit (8.5 ton) (2 ea @ $18,000/ea) 36,000
5 Rooftop AC Unit (7.5 ton) (4 ea @ $16,000/ea) 64,000
6 Rooftop AC Unit (6 ton) (2 ea @ $15,000/ea) 30,000
7 Rooftop AC Unit (4 ton) (3 ea @ $9,000/ea) 27,000
8 Rooftop AC Unit (2 ton) (2 ea @ $6,000/ea) 12,000
9 Make-Up Air Unit (5,300 cfm) 25,000
10 Ductwork/Air Distribution/Curb ADApters 75,000
11 Electrical 35,000
12 Roofing 25,000
13 Demolition/Rigging 25,000
14 Temperature Controls 75,000
15 Testing & Balancing 20,000
16 Commissioning 12,000
Total 739,000