Application ID: 7077
Project Title: Roofing Replacement, Casa Grande
Agency: CGTH
Division: CGTH
Department: NDOC
Project Manager: MHF
Description: This project would provide for a single ply roofing system
Location: Las Vegas
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (85,000 sf @ $1/sf) 85,000
2 Membrane Installation (85,000 sf @ $10.5/sf) 892,500
3 Misc Components (85,000 sf @ $1/sf) 85,000
4 Walk Pads (500 lf @ $2/lf) 1,000
5 Crickets (4 ea @ $500/ea) 2,000
6
7
8
9
10
11
12
13
14
15
16
Total 1,065,500