View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7075
Project Title: Advance Planning: Replace Perimeter Security Fence (SDCC)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: BJW
Description: Design through schematic level documents to remove and replace and upgrade existing perimeter security fence.
Location: Indian Springs
DI_Location_2: 0
Project Description: Project scope includes design through schematic level documents to upgrade and square-off the existing perimeter security fencing at the Southern Desert Correctional Center (SDCC). Scope of work will include new perimeter fencing, new razor wire including razor wire between inside and outside perimeter fence, high mast lights, a perimeter intruder detection system, surveillance infrastructure, and a new perimeter roadway. Construction is planned to be conducted separately with CIP Applications 7157 and 7158.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove Perimeter Security Fence (2,500 lf @ $28/lf) 70,000
2 Relocate Propane Gas Tanks & Concrete Pad 50,000
3 Relocate Switchgear & Transformer 100,000
4 Construct Perimeter Roadway 630,000
5 Install High Mast Lights (5 ea @ $90,000/ea) 450,000
6 Upgrade Existing Perimeter Fence (1,300 lf @ $130/lf) 169,000
7 Install Perimeter Security Fence (12,200 lf @ $235/lf) 2,867,000
8 Perimeter Intruder Detection System (7,400 lf @ $185/lf) 1,369,000
9 Security Electronics, Cameras, Monitors 1,000,000
10
11
12
13
14
15
16
Total 6,705,000