Application ID: 7072
Project Title: Parking Lot Expansion (N. NV Child and Adolescent Services)
Agency: NNCAS
Division: CFS
Department: DHHS
Project Manager: MJM
Description: Expand the lower parking lot at Northern Nevada Child and Adolescent services.
Location: Reno
DI_Location_2: 0
Project Description: This project will expand the existing lower parking lot to accommodate employees and clients during heavy use periods.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Construct Additional 20 Parking Spaces 70,000
2 Earthwork 25,000
3 Drainage 15,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 110,000