View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7070
Project Title: Rehabilitate Roadway Slope (Various)
Agency: NNCAS
Division: CFS
Department: DHHS
Project Manager: BJW
Description: Rehabilitate the McCarran Boulevard roadway slope adjacent to Northern Nevada Child and Adolescent Services, Early Intervention Services and UNR faculties.
Location: Reno
DI_Location_2: 0
Project Description: This project will design and construct roadway slope improvements to the southern McCarran Boulevard roadway slope, from the Evans Road intersection to approximately 1,700 feet west, directly adjacent to the Northern Nevada Child and Adolescent Services (NNCAS), Early Intervention Services (EIS), and University of Nevada facilities. This project will first include a comprehensive geotechnical study to ascertain the cause of slope failures and provide a recommended mitigation. Second, construction is anticipated to include a rock buttress along the entire toe of roadway slope, a mechanically stabilized earth retaining wall at the EIS building, a rip-rap lined ditch to control roadway drainage along the entire top of slope, miscellaneous drainage appurtenances, and replacement of impacted Nevada Department of Transportation (NDOT) right of way fence. A majority of the roadway slope and project improvements will take place within NDOT right of way, and as such, extensive NDOT coordination and permitting will be part of this project. The rip-rap lined ditch is anticipated to be wholly within NDOT right of way.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Excavation & Off Haul (16,000 cy @ $20/cy) 320,000
2 Rock Buttress (1,700 lf @ $850/lf) 1,445,000
3 Retaining Wall (2,500 sf @ $75/sf) 187,500
4 Stormwater Improvements 25,000
5 Remove & Replace Right of Way Fence (1,700 lf @ $30/lf) 51,000
6
7
8
9
10
11
12
13
14
15
16
Total 2,028,500