Application ID: 7069
Project Title: Replace Sanitary Sewer and Upgrade Bathroom (Lost City Museum)
Agency: LostCity
Division: MusHist
Department: T&CultAffr
Project Manager: BJW
Description: Replace the site sanitary sewer, remodel the staff bathroom, and cap abandoned waste fixtures.
Location: Overton
DI_Location_2: 0
Project Description: The project will design and construct a sanitary sewer line replacement, remodel the staff bathroom, restore sanitary sewer to the archeology lab sink, and cap abandoned fixtures and waste vents in the Lost City Museum. The project scope includes replacement of the site sanitary sewer, complete demolition and remodeling of the staff bathroom, and abandonment of existing fixtures and vents that are releasing sewer gas inside the building. The staff bathroom remodel will also bring the facility up to ADA standards, install a single stall shower, as well as replace the plumbing systems.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace Site Sanitary Sewer (500 lf @ $70/lf) 35,000
2 Remodel Staff Bathroom 35,000
3 Cap Abandoned Restroom Fixtures & Waste Vents 10,000
4 Reconnect Archeology Lab Sink to Sanitary Sewer 5,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 85,000