Application ID: 7056
Project Title: Building 1391 Lobby Entrance (Desert Regional Center)
Agency: DRC
Division: ADSD
Department: DHHS
Project Manager: JJD
Description: Remodel Bldg 1391 Lobby/Vestibule to provide secure access point controlled by receptionist.
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project will provide a secure barrier between the main lobby and the office area of the DRC administration building. The project includes design and construction costs for converting the existing vestibule into a controlled barrier between the exterior and the rest of the building. The Reception / Admin Assistant will be moved to an adjacent office with direct view and control of the entrance vestibule.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Interior Renovations 68,000
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 68,000