Application ID: 7054
Project Title: Pavement Maintenance (Desert Regional Center)
Agency: DRC
Division: ADSD
Department: DHHS
Project Manager: MJM
Description: Overlay one parking lot area, crack seal, seal coat and re-stripe the remainder of the pavement.
Location: Las Vegas
DI_Location_2: 0
Project Description: This project would grind and overlay some of the AC pavement, and perform preventative maintenance and striping throughout the DRC portion of the Southern Nevada Mental Health campus.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Grind & Overlay with 2" AC (9,000 sf @ $3/sf) 27,000
2 Crack Seal (125,000 sf @ $.05/sf) 6,250
3 Seal Coat (125,000 sf @ $.3/sf) 37,500
4 Parking Striping 15,000
5.
6
7
8
9
10
11
12
13
14
15
16
Total 85,750