Application ID: 7048
Project Title: ADA Upgrades Building 1301 (Desert Regional Center)
Agency: DRC
Division: ADSD
Department: DHHS
Project Manager: MCR
Description: Remodel Interior and Exterior residential building for compliance with the ADA
Location: Las Vegas
DI_Location_2: 0
Project Description: This Project will remodel the interior and exterior of building 1301 at Desert Regional Center. The work will consist of bathrooms, kitchen, door hardware, thresholds and casework alterations and appliances to comply with the American with Disabilities Ac

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Kitchen Remodel 29,500
2 Remodel Bathrooms (3 ea @ $21,240/ea) 63,720
3 Remodel Hall Bathroom 14,160
4 Replace Door Hardware (20 ea @ $400/ea) 8,000
5 Install Thresholds (2 ea @ $350/ea) 700
6 Demo 4 Rooms (6 ea @ $1,180/ea) 7,080
7 Finish Carpentry 4 Rooms (6 ea @ $2,600/ea) 15,600
8 Misc Signage 1,180
9 Under Slab Piping Replacement (2,924 sf @ $10/sf) 29,240
10 Remove Concrete at Exterior Door (400 sf @ $2/sf) 800
11 Replace Concrete at Exteior Door (400 sf @ $10/sf) 4,000
12
13
14
15
16
Total 173,980