View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7045
Project Title: Fire Suppression Installation (Lost City Museum)
Agency: Museum
Division: MusHist
Department: T&CultAffr
Project Manager: KRS
Description: Install and Upgrade Fire Suppression System throughout the facility.
Location: Overton
DI_Location_2: 0
Project Description: The scope of this project is to replace the existing fire alarm and install a new pre-action fire sprinkler system. The work also includes the installation of a security/intrusion alarm system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Underground Supply Pipe (330 lf @ $100/lf) 33,000
2 Trenching Under Existing Railroad Tracks 15,000
3 Pre-Action Fire Riser & Controls 12,000
4 Fire Sprinkler Installation (22,434 sf @ $10/sf) 224,340
5 Fire Alarm Installation (23,594 sf @ $2.25/sf) 53,087
6 Riser Room Construction 4,500
7 Intrusion Alarm (23,594 ea @ $1.25/ea) 29,493
8 Painting of Fire Pipes to Blend Into Facility 5,000
9
10
11
12
13
14
15
16
Total 376,419