AppID19258
I. Administrative Section 
1. Project Name: Repair Roofs
2. Project Description (One Sentence): This project replaces roofs on all or part of five existing campus buildings.
3a. Project Location: County: Washoe
3b. Project Location: City: Reno
4. Department (department requesting project): NSHE
5. Division (division requesting project): UNR
6. Agency (agency requesting project): Planning
7. Agency contact person: Dean Hitchcock
8. Contact phone: 775-784-1022
9. Contact email: dhitchcock@unr.edu
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project).
11. Has this project been previously requested in a prior CIP? Yes
12. SPWD 4 digit Building No. (for existing buildings)
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
16. Project Description: This project replaces approximately 267,000 square feet of roofs on all or portions of ten existing campus buildings: Sports Medicine Complex (1993 roof), Church Fine Arts (1992 roof), Fleischmann Agriculture (1991 roof), Continuing Education Building (1990 roof), Knudtsen Resource Center(1987 Roof), Lombardi Recreation Center (1973 Roof), Agricultural Education (1987 Roof), Renewable Resource Center (1987 Roof), Computing Center (1990 Roof), and the Sara Fleischmann Building (1994 Roof). mold growth.
17. Project Justification: These roofs are currently leaking, are out of warranty, and have outlived their useful life. During inclement weather, leaking causes damage to equipment, building systems such as ceilings and walls, and results in increased repair costs and potential mold growth.
18. Project Background Information: Over the past several years, maintenance level patching has not kept pace with roof deterioration. Rain and snow events result in leaking, additional facility damage, and hinders the use of facility space for intended purposes.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced:
19b. Year existing equipment was installed:
19c. Manufacturer of existing equipment:
19d. Model of existing equipment:
19e. Are there any known hazardous materials?
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.): Possibility of asbestos.
20b. Will the site require any hazardous material abatement? Unknown
21. Ramifications if the Project is not Approved (short essay): Continued damage to the interior of the building as well as equipment, property, and documents. When leaks occur it disrupts or entirely stops essential functions in the building and among staff.
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Possibility of mold inside the building that would threaten occupants' health. Legal risk of staff being unable to perform their essential functions or use the building.
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? No
23b. Explain:
23c. Has any design work been completed on the proposed project? Yes
23d. What is the latest date this project could be completed without disrupting your program? 10/1/2020
23e. What is the driving proposed completion date?
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased):
25. Offsite construction:
26. On-site Development: 5,000,000
27. Utility connection fees:
28. Water rights deeded:
29. Furniture, Fixtures and Equipment:
30. Specialty equipment:
31. Data and network equipment:
32. Telephone equipment costs:
33. Moving:
34. Renovation of vacated space:
35a. Correction of known deficiencies:
35b. (describe deficiencies)
36a. Any known commitments:
36b. (describe commitments)
37a. Known hazardous material abatement:
37b. (describe hazardous materials)
38. Total project costs: 5,000,000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal
39c. State 5,000,000
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding):
39f. Total: 5,000,000
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name
40b. Phone Number
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres)
42. Will this project require new parking spaces?
43. Are utilities available to site?
44. Will project require relocation of existing utilities?
45. Are there any required offsite improvements (or right-of-way dedications)?
46. Is the site in a flood plain?
47. Is the site in an airport impact zone?
48. Does the site contain any underground storage tanks?
49. Does the site contain any adverse soil conditions?
50. Will the site require an environmental assessment?
51. Will rezoning or a special use permit be required?
52. Will any Utility connection fees need to be paid?
53. Will any water rights need to be deeded?
54. Will construction traffic degrade existing access or facilities?
55. Will the site require any hazardous material abatement?
56a. Other site considerations affecting cost? (describe):
56b. Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs?
59. Usable Square footage required (including storage space)
59a. New Construction SF:
59b. Remodel/Renovation SF:
59c. Addition SF
59d.Total project SF:
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) :
61. Approximate number of staff to occupy facility:
62. Approximate number of visitors per day:
63. Will this project require funding for any furnishings, fixtures and equipment?
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks):
65. How many years of future growth will this project accommodate?
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:

Submit