Submitted Application for a 2019 CIP Project

AppID19173
I. Administrative Section 
1. Project Name: Roofing Replacement on North Annex Building
2. Project Description (One Sentence): Replace leaking roof on North Annex Building at Nevada State Museum.
3a. Project Location: County: Carson City
3b. Project Location: City: Carson City
4. Department (department requesting project): Cultural Affairs
5. Division (division requesting project): Museums & History
6. Agency (agency requesting project): Nevada State Museum
7. Agency contact person: Myron Freedman
8. Contact phone: 775 687 4810 x 226
9. Contact email: mfreedman@nevadaculture.org
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 11
11. Has this project been previously requested in a prior CIP? No
12. SPWD 4 digit Building No. (for existing buildings) 2027
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
16. Project Description: Replace roofing on North Annex Building at Nevada State Museum.
17. Project Justification: Current roof was installed in 1999. It leaked last year, and has ongoing leaks. The North Annex houses major anthropology collections with irreplaceable artifacts, including the Native American basket collection with items valued in the millions of dollars. The NSM is an accredited AAM museum, and any deterioration in collections housing could threaten accreditation.
18. Project Background Information: Current roof is approximately 5,000 square feet and was installed in 1999. The warranty has expired. It leaked last year, and is leaking this year. The roof has ongoing leaks. The North Annex houses major State of Nevada anthropology collections with irreplaceable artifacts, including the Native American basket collection with items valued in the millions of dollars.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced:
19b. Year existing equipment was installed:
19c. Manufacturer of existing equipment:
19d. Model of existing equipment:
19e. Are there any known hazardous materials? No
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.):
20b. Will the site require any hazardous material abatement? No
21. Ramifications if the Project is not Approved (short essay):
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Leaks from the roof may lead to mold and mildew growth, which is unhealthy for staff and a threat to irreplaceable artifacts made from organic materials. The museum receives donations of artifacts and guarantees their preservation and safekeeping to donors.
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? No
23b. Explain:
23c. Has any design work been completed on the proposed project? No
23d. What is the latest date this project could be completed without disrupting your program? 08/31/2020
23e. What is the driving proposed completion date? Mitigation of leaking roof to preserve appropriate environmental condition for irreplaceable artifacts valued in the millions of dollars.
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased):
25. Offsite construction:
26. On-site Development:
27. Utility connection fees:
28. Water rights deeded:
29. Furniture, Fixtures and Equipment:
30. Specialty equipment:
31. Data and network equipment:
32. Telephone equipment costs:
33. Moving:
34. Renovation of vacated space:
35a. Correction of known deficiencies: 240,000
35b. (describe deficiencies) Leaking roof. Current roof is approximately 5,000 square feet and was installed in 1999. The warranty has expired. It leaked last year, and is leaking this year.
36a. Any known commitments:
36b. (describe commitments)
37a. Known hazardous material abatement:
37b. (describe hazardous materials)
38. Total project costs: 240,000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal
39c. State 240,000
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding):
39f. Total: 240,000
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name
40b. Phone Number
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres)
42. Will this project require new parking spaces? No
43. Are utilities available to site?
44. Will project require relocation of existing utilities?
45. Are there any required offsite improvements (or right-of-way dedications)?
46. Is the site in a flood plain?
47. Is the site in an airport impact zone?
48. Does the site contain any underground storage tanks?
49. Does the site contain any adverse soil conditions?
50. Will the site require an environmental assessment?
51. Will rezoning or a special use permit be required?
52. Will any Utility connection fees need to be paid?
53. Will any water rights need to be deeded?
54. Will construction traffic degrade existing access or facilities?
55. Will the site require any hazardous material abatement?
56a. Other site considerations affecting cost? (describe):
56b. Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs?
59. Usable Square footage required (including storage space)
59a. New Construction SF:
59b. Remodel/Renovation SF:
59c. Addition SF
59d.Total project SF:
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) :
61. Approximate number of staff to occupy facility:
62. Approximate number of visitors per day:
63. Will this project require funding for any furnishings, fixtures and equipment?
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks):
65. How many years of future growth will this project accommodate?
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: