Submitted Application for a 2019 CIP Project

AppID19158
I. Administrative Section 
1. Project Name: Expand Fire Alarm System
2. Project Description (One Sentence): Expand the fire alarm system to all areas of building 1300 and connect it to the main fire alarm panel located in building 1391.
3a. Project Location: County: Clark
3b. Project Location: City: Las Vegas
4. Department (department requesting project): DHHS
5. Division (division requesting project): Aging & Disability Services
6. Agency (agency requesting project): Desert Regional Center
7. Agency contact person: Darrel Hansen
8. Contact phone: 702.486.6333
9. Contact email: DLHansen@adsd.nv.gov
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 5
11. Has this project been previously requested in a prior CIP? Unknown
12. SPWD 4 digit Building No. (for existing buildings)
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
16. Project Description: Expand the fire alarm system to all areas of building 1300 and connect it to the main fire alarm panel located in building 1391.
17. Project Justification: Building 1300 is a multi-use facility, it houses up to six individuals living at the Intermediate Care Facility for Individuals with Intellectual Disabilities (ICF) in the west wing and various staff in the east, south, and north wings. The fire alarm system currently does not service all areas of the building and needs to be expanded. If a fire were to occur in an unmonitored section of the building significant damage could occur before help could be summoned. It also places individuals living at the ICF at greater risk because of the potential delayed notification.
18. Project Background Information: The fire alarm system in building 1300 was initially installed only in areas being utilized by Southern Nevada Adult Mental Health Services. Areas occupied by Desert Regional Center were not included in this initial installation.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced:
19b. Year existing equipment was installed:
19c. Manufacturer of existing equipment:
19d. Model of existing equipment:
19e. Are there any known hazardous materials? Unknown
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.):
20b. Will the site require any hazardous material abatement? Unknown
21. Ramifications if the Project is not Approved (short essay): Individuals living at the ICF and staff will continue to be at risk due to the potential delayed notification if a fire occurred in an unmonitored area of the building.
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay):
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? Unknown
23b. Explain:
23c. Has any design work been completed on the proposed project? Unknown
23d. What is the latest date this project could be completed without disrupting your program? 06-30-2020
23e. What is the driving proposed completion date? Life Safety
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased):
25. Offsite construction:
26. On-site Development:
27. Utility connection fees:
28. Water rights deeded:
29. Furniture, Fixtures and Equipment:
30. Specialty equipment:
31. Data and network equipment:
32. Telephone equipment costs:
33. Moving:
34. Renovation of vacated space:
35a. Correction of known deficiencies:
35b. (describe deficiencies)
36a. Any known commitments:
36b. (describe commitments)
37a. Known hazardous material abatement:
37b. (describe hazardous materials)
38. Total project costs: 120000.00
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal
39c. State
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding):
39f. Total: 120000.00
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name
40b. Phone Number
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres)
42. Will this project require new parking spaces? No
43. Are utilities available to site? Yes
44. Will project require relocation of existing utilities? Unknown
45. Are there any required offsite improvements (or right-of-way dedications)? Unknown
46. Is the site in a flood plain? Unknown
47. Is the site in an airport impact zone? Unknown
48. Does the site contain any underground storage tanks? Unknown
49. Does the site contain any adverse soil conditions? Unknown
50. Will the site require an environmental assessment? Unknown
51. Will rezoning or a special use permit be required? Unknown
52. Will any Utility connection fees need to be paid? Unknown
53. Will any water rights need to be deeded? No
54. Will construction traffic degrade existing access or facilities? Unknown
55. Will the site require any hazardous material abatement? Unknown
56a. Other site considerations affecting cost? (describe): Unknown
56b. Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs? Unknown
59. Usable Square footage required (including storage space)
59a. New Construction SF:
59b. Remodel/Renovation SF:
59c. Addition SF
59d.Total project SF:
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Institutional
61. Approximate number of staff to occupy facility: 40
62. Approximate number of visitors per day: 15
63. Will this project require funding for any furnishings, fixtures and equipment? Unknown
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks): Unknown
65. How many years of future growth will this project accommodate?
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:

Submit