1. Project Name: CCA interior and exterior door replacement
2. Project Description (One Sentence): remove and replace complete door system except frames in approx. 26 exterior doors an 60 interior doors.
3a. Project Location: County: Clark
3b. Project Location: City: N. Las Vegas
4. Department (department requesting project): Military
5. Division (division requesting project): Nevada Army National Guard
6. Agency (agency requesting project):
7. Agency contact person: tom mcelroy
8. Contact phone: 775 887-7288
9. Contact email:
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project).
11. Has this project been previously requested in a prior CIP? No
12. SPWD 4 digit Building No. (for existing buildings)
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
16. Project Description: Door systems are worn out and lack replacement components in building constructed in 1995. Keep existing frames where possible. Replace door leafs and accessories at approx 26 exterior doors and 60 interior doors.
17. Project Justification: Each door has worn out parts to include hinges, latches, closures, panic bars, strikes, center mullions, locks, deadbolts, thresholds, kick plates, coordinators, etc. Building over-use shows in 25 year old building. Paving projects have directed water into building along asphalt interfaces.
18. Project Background Information: over use, and paving maintenance have door systems failing.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced:
19b. Year existing equipment was installed:
19c. Manufacturer of existing equipment:
19d. Model of existing equipment:
19e. Are there any known hazardous materials? No
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.):
20b. Will the site require any hazardous material abatement? No
21. Ramifications if the Project is not Approved (short essay): Inability to lock doors, maintain security, keep water out, lack of spare parts, beyond skill sets of maintenance personnel
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Waer into building along asphalt areas, inability to lock doors, use panic bars, or secure personal identifiable information and OPSEC.
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? No
23b. Explain:
23c. Has any design work been completed on the proposed project? No
23d. What is the latest date this project could be completed without disrupting your program? fall 2020
23e. What is the driving proposed completion date? Existing failure of doors and associated components
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased): 0
25. Offsite construction: 0
26. On-site Development: 0
27. Utility connection fees: 0
28. Water rights deeded: 0
29. Furniture, Fixtures and Equipment: 0
30. Specialty equipment: 0
31. Data and network equipment: 0
32. Telephone equipment costs: 0
33. Moving: 0
34. Renovation of vacated space: 0
35a. Correction of known deficiencies: 0
35b. (describe deficiencies)
36a. Any known commitments: 0
36b. (describe commitments)
37a. Known hazardous material abatement: 0
37b. (describe hazardous materials)
38. Total project costs: 280,000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal 140000
39c. State 140000
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding): Request state provide PM&I funding
39f. Total: 280,000
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name tom mcelroy
40b. Phone Number 775 887 7288
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres) 0
42. Will this project require new parking spaces? No
43. Are utilities available to site? No
44. Will project require relocation of existing utilities? No
45. Are there any required offsite improvements (or right-of-way dedications)? No
46. Is the site in a flood plain? No
47. Is the site in an airport impact zone? No
48. Does the site contain any underground storage tanks? No
49. Does the site contain any adverse soil conditions? No
50. Will the site require an environmental assessment? No
51. Will rezoning or a special use permit be required? No
52. Will any Utility connection fees need to be paid? No
53. Will any water rights need to be deeded? No
54. Will construction traffic degrade existing access or facilities? No
55. Will the site require any hazardous material abatement? No
56a. Other site considerations affecting cost? (describe): No
56b. Describe Site Considerations: 25 year old overused building. Need design work prior to construction such as at CSMS-1 Carson City work performed by H&K architects.
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs? No
59. Usable Square footage required (including storage space)
59a. New Construction SF: 0
59b. Remodel/Renovation SF: 76000
59c. Addition SF 0
59d.Total project SF: 76000
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
61. Approximate number of staff to occupy facility: 650
62. Approximate number of visitors per day: 45
63. Will this project require funding for any furnishings, fixtures and equipment? No
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks): No
65. How many years of future growth will this project accommodate? 25
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: Request State provide funding for PM&I, permitting and plan check.

Submit


NOTE:  IF YOU ARE THE “AGENCY CONTACT PERSON”, AND HAVE NOT BEEN CONTACTED BY THE ASSIGNED PROJECT MANAGER BY APRIL 16, 2018, PLEASE CONTACT THEM.