1. Project Name: NNAMHS-building 3 renovation
2. Project Description (One Sentence): A project to renovate various utilities in building 3.
3a. Project Location: County: Washoe
3b. Project Location: City: Sparks
4. Department (department requesting project): DHHS
5. Division (division requesting project): Public & Behavioral Health
6. Agency (agency requesting project): NNAMHS
7. Agency contact person: Kurt Green
8. Contact phone: 775-688-2030
9. Contact email:
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 131
11. Has this project been previously requested in a prior CIP?
12. SPWD 4 digit Building No. (for existing buildings)
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned?
15. If the facility is existing, is it State owned?
II. Narrative Section 
16. Project Description: This project will renovate various features of building 3, such as new plumbing, restroom remodels, lighting upgrades, HVAC upgrades and equipment replacement. This project will work most efficiently with other FCA recommended project #s 7354-7355-7356-7357 that include window, electrical, ceiling, and flooring replacement.
17. Project Justification: Building 3 was closed down in 2008, the need for additional space for new and existing agency services has become a necessity. Building 3 is still partially open, the lower east wing houses the pharmacy and other related services. Building 3 is the natural choice for renovation based on its condition and proximity to related services, and architectural similarities to building 1 built in the same time period and designed by the same architect. Building 3 is a candidate for historical preservation built in 1925 and should be considered for such protection.
18. Project Background Information: Building 3 was closed down in 2008, as the result of the consolidated services building (project #C-730A) being built and the demolition of the heat plant that provided heat to the building. The consolidated services building project was shelved due to economic constraints and the need to reopen the building has emerged.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced: Various
19b. Year existing equipment was installed: 1925 to modern era
19c. Manufacturer of existing equipment: Unknown
19d. Model of existing equipment: Unknown
19e. Are there any known hazardous materials? Unknown
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.):
20b. Will the site require any hazardous material abatement? Unknown
21. Ramifications if the Project is not Approved (short essay): Building 3 will partially remain open and continue to need renovation, the cost of renovation will go up as the material condition of the building continues to deteriorate.
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Many life/safety aspects of building 3 will improve, and upgrades to the HVAC and electrical systems will prevent injury and death. Building break-ins will be reduced resulting in safer working conditions for staff and clients.
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? Unknown
23b. Explain:
23c. Has any design work been completed on the proposed project? No
23d. What is the latest date this project could be completed without disrupting your program? 06/30/18
23e. What is the driving proposed completion date? The availability of funding and the need for additional space for agency needs.
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased):
25. Offsite construction:
26. On-site Development:
27. Utility connection fees:
28. Water rights deeded:
29. Furniture, Fixtures and Equipment:
30. Specialty equipment:
31. Data and network equipment:
32. Telephone equipment costs:
33. Moving:
34. Renovation of vacated space:
35a. Correction of known deficiencies:
35b. (describe deficiencies)
36a. Any known commitments:
36b. (describe commitments)
37a. Known hazardous material abatement:
37b. (describe hazardous materials)
38. Total project costs: 500,000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal
39c. State 500,000
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding):
39f. Total: 500,000
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name
40b. Phone Number
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres)
42. Will this project require new parking spaces?
43. Are utilities available to site?
44. Will project require relocation of existing utilities?
45. Are there any required offsite improvements (or right-of-way dedications)?
46. Is the site in a flood plain?
47. Is the site in an airport impact zone?
48. Does the site contain any underground storage tanks?
49. Does the site contain any adverse soil conditions?
50. Will the site require an environmental assessment?
51. Will rezoning or a special use permit be required?
52. Will any Utility connection fees need to be paid?
53. Will any water rights need to be deeded?
54. Will construction traffic degrade existing access or facilities?
55. Will the site require any hazardous material abatement?
56a. Other site considerations affecting cost? (describe):
56b. Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs?
59. Usable Square footage required (including storage space)
59a. New Construction SF:
59b. Remodel/Renovation SF:
59c. Addition SF
59d.Total project SF:
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) :
61. Approximate number of staff to occupy facility:
62. Approximate number of visitors per day:
63. Will this project require funding for any furnishings, fixtures and equipment?
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks):
65. How many years of future growth will this project accommodate? 30
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: