Submitted Application from prior CIP Planning Cycle

AppID7352
I. Administrative Section 
1. Project Name: NNAMHS building 22 electrical upgrade
2. Project Description (One Sentence): A project to upgrade the electrical system for building 22.
3a. Project Location: County: Washoe
3b. Project Location: City: Sparks
4. Department (department requesting project): DHHS
5. Division (division requesting project): Public & Behavioral Health
6. Agency (agency requesting project): NNAMHS
7. Agency contact person: Kurt Green
8. Contact phone: 775-688-2030
9. Contact email: kgreen@health.nv.gov
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (e.g., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project).
11. Has this project been previously requested in a prior CIP? No
12. SPWD 4 digit Building No. (for existing buildings) 0353
13. Facility Condition Analysis Project No. (if recommended) 0353ELE2
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
16. Project Description: This project would upgrade the entire electrical system in building 22 to meet the evolving needs of this building and bring it up to modern code standards.
17. Project Justification: The building was built before the high demand for modern electrical services were required for such things as computers, gas fired heaters, evaporative coolers, life/safety devices and other modern electric devices. The building is now beyond its designed electrical capacity and in need of renovation.
18. Project Background Information: Building 22 has metamorphosed into a hybrid use building of various services that have changed the electrical loads and placed a heavy burden on the electrical system.
19. Mechanical and/or Electrical Equipment Replacement Projects:
19a. Type of equipment to be replaced: Wiring panels and switches
19b. Year existing equipment was installed: 1959
19c. Manufacturer of existing equipment: Various
19d. Model of existing equipment: Various
19e. Are there any known hazardous materials? Unknown
Environmental Considerations
20a. Hazardous Materials (Asbestos, Lead Paint, etc.):
20b. Will the site require any hazardous material abatement? Unknown
21. Ramifications if the Project is not Approved (short essay): Building 22 will continue to be weighted with a heavy electrical load condition with inadequate system components that will ultimately result in failure.
Health, Life Safety, and/or Legal Issues
22. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Building 22 power system upgrades will prevent electrical related injuries from occurring especially in the maintenance shop where electrical use is extreme.
23. Proposed Project Schedule Impacts/Issues
23a. Will this project require relocating personnel or vacating the building for any period of time? Unknown
23b. Explain:
23c. Has any design work been completed on the proposed project? No
23d. What is the latest date this project could be completed without disrupting your program? 06/30/18
23e. What is the driving proposed completion date? The availability of funding and the need for safe electrical systems.
III. Preliminary Construction Cost Estimate and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
24. Land (if land must be purchased):
25. Offsite construction:
26. On-site Development:
27. Utility connection fees:
28. Water rights deeded:
29. Furniture, Fixtures and Equipment:
30. Specialty equipment:
31. Data and network equipment:
32. Telephone equipment costs:
33. Moving:
34. Renovation of vacated space:
35a. Correction of known deficiencies:
35b. (describe deficiencies)
36a. Any known commitments:
36b. (describe commitments)
37a. Known hazardous material abatement:
37b. (describe hazardous materials)
38. Total project costs: 144,000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
39. Proposed funding of total project cost:
39a. Agency:
39b. Federal
39c. State 144,000
39d. Other/Donor
39e. (describe source of 'Other/ Donor' funding):
39f. Total: 144,000
40. Agency point of contact for outisde funding if 39a, 39b, or 39c funding sources are providing funds.
40a. Name
40b. Phone Number
40c. Email Address
IV. Site Analysis Section 
Site Analysis (New construction only)
41. Estimated land area to be acquired (acres)
42. Will this project require new parking spaces?
43. Are utilities available to site?
44. Will project require relocation of existing utilities?
45. Are there any required offsite improvements (or right-of-way dedications)?
46. Is the site in a flood plain?
47. Is the site in an airport impact zone?
48. Does the site contain any underground storage tanks?
49. Does the site contain any adverse soil conditions?
50. Will the site require an environmental assessment?
51. Will rezoning or a special use permit be required?
52. Will any Utility connection fees need to be paid?
53. Will any water rights need to be deeded?
54. Will construction traffic degrade existing access or facilities?
55. Will the site require any hazardous material abatement?
56a. Other site considerations affecting cost? (describe):
56b. Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
57. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
58. Has any advanced planning occurred in previous CIPs?
59. Usable Square footage required (including storage space)
59a. New Construction SF:
59b. Remodel/Renovation SF:
59c. Addition SF
59d.Total project SF:
60. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) :
61. Approximate number of staff to occupy facility:
62. Approximate number of visitors per day:
63. Will this project require funding for any furnishings, fixtures and equipment?
64. For existing facilities, are there any known hazardous materials? (e.g., Asbestos, lead paint or underground storage tanks):
65. How many years of future growth will this project accommodate?
66. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:

Submit


NOTE:  AFTER SUBMITTING THE COMPLETED APPLICATION, A PROJECT MANAGER FROM THE PUBLIC WORKS DIVISION WILL CONTACT YOU TO REVIEW THIS APPLICATION.