I. Administrative Section 
1. Project Name: Connect Henderson Armory to Municipal sewer
2. Project Description (One Sentence): Connect Henderson Armory to Sewer, pay City of HEnderson Sewer Connection fees, demolish existing septic system.
3a. Project Location: County: Clark
3b. Project Location: City: Henderson
4. Department (department requesting project): Military
5. Division (division requesting project): Nevada Army National Guard
6. Agency (agency requesting project):
7. Agency contact person: Tom McElroy
8. Contact phone: 775-887-7288
9. Contact email: thomas.c.mcelroy2.mil@mail.mil
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 22
11. Has this project been previously requested in a prior CIP? Yes
12. SPWD 4 digit Building No. (for existing buildings) 9912
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? Yes
II. Narrative Section 
1. Project Description: Henderson armory is on 1970 septic system. Disconnect septic systema dn demolish. Hook up to City of Henderson sewer.
2. Project Justification: Septic system design available. Old shop floor drains went into septic system. Septic system limits building and site development or expansion
3. Project Background Information:
4. Mechanical and/or Electrical Equipment Replacement Projects:
a. Type of equipment to be replaced: 0
b. Year existing equipment was installed: 1970
c. Manufacturer of existing equipment:
d. Model of existing equipment:
e. Are there any known hazardous material abatement? Unknown
5. Ramifications if the Project is not Approved (short essay): NVARNG will not be able to expand or do further site development at Henderson and would require mor property elsewhere.
Health, Life Safety, and/or Legal Issues
6. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Armory will have limited use and no further development due to septic limitations.
7. Proposed Project Schedule Impacts/Issues
a. Will this project require relocating personnel or vacating the building for any period of time? Unknown
Explain: possible use or porta potties while connectiont to city sewer or hot tapping operations.
b. Has any design work been completed on the proposed project? Yes
c. What is the latest date this project could be completed without disrupting your program? 12/30/17
d. What is the driving proposed completion date? regulatory and site development limitations
III. Preliminary Construction and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land (if land must be purchased): 0
2. Off-site construction: 75,000
3. On-site Development: 50,000
4. Utility connection fees: 125,000
5. Water rights deeded: 0
6. Furniture, Fixture and Equipment: 0
7. Specialty equipment: 0
8. Data and network equipment: 0
9. Telephone equipment costs: 0
10. Moving: 0
11. Renovation of vacated space: 0
12. Correction of known deficiencies:
(describe deficiencies)
13. Any known commitments:
(describe commitments)
14. Known hazardous material abatement:
(describe hazardous materials)
15. Total project costs: 0
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost:
a. Agency:
b. Federal 125,000
c. Other/Donor
d. State
(describe source of 'Other/ Donor' funding): NVARNG requests PM&I be fundded by the State.
Total: 250,000
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name tom mcelroy
b. Phone Number 775-887-7288
c. Email Address thomas.c.mcelroy2.mil@mail.mil
IV. Site Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres) 0
2. Will this project require new parking spaces? No
3. Are utilities available to site? Yes
4. Will project require relocation of existing utilities? Unknown
5. Are there any required off-site improvements (or right-of-way dedications)? Yes
6. Is the site in a flood plain? No
7. Is the site in an airport impact zone? No
8. Does the site contain any underground storage tanks? Unknown
9. Does the site contain any adverse soil conditions? Unknown
10. Will the site require an environmental assessment? Unknown
11. Will rezoning or a special use permit be required? Unknown
12. Will any Utility connection fees need to be paid? Yes
13. Will any water rights need to be deeded? No
14. Will construction traffic degrade existing access or facilities? Unknown
15. Will the site require any hazardous material abatement? Unknown
16. Other site considerations affecting cost? (describe): Unknown
Describe Site Considerations: street cut and connection to city sewer
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
2. Has any advanced planning occurred in previous CIPs? Yes
3. Usable Square footage required (including storage space)
a. New Construction SF: 0
b. Remodel/Renovation SF: 0
c. Addition SF 0
d.Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
5. Approximate number of staff to occupy facility:
6. Approximate number of visitors per day:
7. Will this project require funding for any furnishings, fixtures and equipment? No
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): No
9. How many years of future growth will this project accommodate? 9
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: none