I. Administrative Section 
1. Project Name: Fallon Readiness Center Front Parking Lot Replacement
2. Project Description (One Sentence): Replace alligatored AC paving, curb and gutter at Fallon Readiness Center front parking lot.
3a. Project Location: County: Churchill
3b. Project Location: City: Fallon
4. Department (department requesting project): Military
5. Division (division requesting project): Nevada Army National Guard
6. Agency (agency requesting project): N/A
7. Agency contact person: Richard Vigni
8. Contact phone: 775 887-7283
9. Contact email: richard.vigni@us.army.mil
The Department ranking of this project:
10. The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 9
11. Has this project been previously requested in a prior CIP? Unknown
12. SPWD 4 digit Building No. (for existing buildings) 0678
13. Facility Condition Analysis Project No. (if recommended)
14. Is the property State Owned? Yes
15. If the facility is existing, is it State owned? No
II. Narrative Section 
1. Project Description: Remove existing AC paving, curb and gutter at front parking lot and replace with new.
2. Project Justification: Existing POV AC paving and associated concrete curb & gutter that serves POV parking at the front of Fallon Readiness Center is severely delaminated, cracked and has reached complete failure several years ago. A complete replacement of these elements is required for a functional parking lot. Existing POV lot does not drain and is badly spalded with exposed aggregate.
3. Project Background Information: submitted in previous CIP.
4. Mechanical and/or Electrical Equipment Replacement Projects:
a. Type of equipment to be replaced: N/A
b. Year existing equipment was installed:
c. Manufacturer of existing equipment:
d. Model of existing equipment:
e. Are there any known hazardous material abatement? No
5. Ramifications if the Project is not Approved (short essay): AC paved parking area will continue to deteriorate and will become unusable for its intended purpose.
Health, Life Safety, and/or Legal Issues
6. Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): The paved surface is currently delaminating, cracking and raveling to the extent of creating a tripping hazard to personnel who walk the parking surface.
7. Proposed Project Schedule Impacts/Issues
a. Will this project require relocating personnel or vacating the building for any period of time? No
Explain:
b. Has any design work been completed on the proposed project? No
c. What is the latest date this project could be completed without disrupting your program? 9/2015
d. What is the driving proposed completion date? Usability of the parking area.
III. Preliminary Construction and Funding Sources Section 
Preliminary Construction Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land (if land must be purchased):
2. Off-site construction:
3. On-site Development:
4. Utility connection fees:
5. Water rights deeded:
6. Furniture, Fixture and Equipment:
7. Specialty equipment:
8. Data and network equipment:
9. Telephone equipment costs:
10. Moving:
11. Renovation of vacated space:
12. Correction of known deficiencies:
(describe deficiencies)
13. Any known commitments:
(describe commitments)
14. Known hazardous material abatement:
(describe hazardous materials)
15. Total project costs:
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost:
a. Agency:
b. Federal 150000
c. Other/Donor
d. State 150000
(describe source of 'Other/ Donor' funding): NVARNG asks that all PM&I,plaqn check and permitting costs are picked up by the State of Nevada.
Total: 300000
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name Richard Vigni
b. Phone Number 775 887-7283
c. Email Address richard.vigni@us.army.mil
IV. Site Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres)
2. Will this project require new parking spaces?
3. Are utilities available to site?
4. Will project require relocation of existing utilities?
5. Are there any required off-site improvements (or right-of-way dedications)?
6. Is the site in a flood plain?
7. Is the site in an airport impact zone?
8. Does the site contain any underground storage tanks?
9. Does the site contain any adverse soil conditions?
10. Will the site require an environmental assessment?
11. Will rezoning or a special use permit be required?
12. Will any Utility connection fees need to be paid?
13. Will any water rights need to be deeded?
14. Will construction traffic degrade existing access or facilities?
15. Will the site require any hazardous material abatement?
16. Other site considerations affecting cost? (describe):
Describe Site Considerations:
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
2. Has any advanced planning occurred in previous CIPs? Unknown
3. Usable Square footage required (including storage space)
a. New Construction SF:
b. Remodel/Renovation SF:
c. Addition SF
d.Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) :
5. Approximate number of staff to occupy facility:
6. Approximate number of visitors per day:
7. Will this project require funding for any furnishings, fixtures and equipment?
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks):
9. How many years of future growth will this project accommodate? 20
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: