Submitted Application for a 2013 CIP Project

View all 2013 CIP Applications.              

AppID3278
I. Administrative Section 
Project Name: Reno Headquarters – Boiler and cooling tower
Project Description (One Sentence): Remove all the HVAC equipment and replace it with new boilers and a cooling tower.
Project Location: County: Washoe
Project Location: City: Reno
Department (department requesting project): Wildlife
Division (division requesting project): N/A
Agency (agency requesting project): N/A
Agency contact person: Ron Cothran
Contact phone: 7758138456
Contact email: rcothran@ndow.org
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 3
Has this project been previously requested in a prior CIP? Yes
SPWD 4 digit Building No. (for existing buildings) 9924
Facility Condition Analysis Project No. (if recommended) 0277HVA1
II. Narrative Section 
Project Justification (Essay)
Project Description: This project would provide for installation of a new central HVAC system to provide conditioning for the entire building. The new system will most likely include altering the existing duct work and adding new duct work. This project includes removal and disposal of the existing HVAC units and all required connections to utilities. This also includes an energy management system to be installed as part of this project.
Project Justification: There are fourteen separate HVAC units servicing the building. They were installed at various times, but are all at least twenty years old. Each unit serves a particular portion of the building which causes the conditioned spaces to be unbalanced and forces some of the units to be overworked. These older units are not energy efficient, don’t meet code and some are original to the building dating back to the 1960’s. They have reached the end of their expected and useful life. Many have been identified as having rusting or even very close to have cracked heat exchangers.
Project Background Information: The Department of Wildlife’s headquarters building was constructed in early 1960’s. Some of the furnaces are original to the building. Some of the HVAC units are from the 60’s, 70’s and 80’s with standing pilots and are not energy efficient.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced: Packaging units and split systems.
Year existing equipment was installed: 60’s, 70’s and 80’s
Manufacturer of existing equipment: The manufacturer of existing equipment varies.
Model of existing equipment: Many
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? Unknown
Ramifications if the Project is not Approved
(Short Essay): The heat exchangers will crack and the units will have to be shut down.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Under the current circumstances a faulty heat exchanger can have serious health effects. In the worst-case scenarios, Carbon Monoxide (CO) has caused individuals in a building filled with leaking CO to fall into a permanent sleep and die. CO is colorless and odorless and works very fast in high concentration. A concentration of 1500 PPM can kill in 15 minutes.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? Unknown
Explain:
Has any design work been completed on the proposed project? No
What is the latest date this project could be completed without disrupting your program? any
What is the driving proposed completion date?
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased):
2. Off-site construction cost:
3. On-site connection fees: 441000
4. Utility connection fees:
5. Water rights deeded:
6. Furniture, Fixture and equipment costs:
7. Specialty equipment costs
8. Data and network equipment costs:
9. Telephone equipment costs:
10. Moving costs:
11. Costs for renovation of vacated space:
12. Costs for correction of known deficiencies:
(describe deficiencies)
13. Costs of any known commitments:
(describe commitments)
14. Costs of any hazardous material abatement:
(describe hazardous materials)
15. Total project costs:
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost:
a. Agency:
b. Federal
c. Other/Donor
d. State 1
(describe source of 'Other' funding):
Total: 441001
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres)
2. Will this project require new parking spaces? No
3. Are utilities available to site? Yes
4. Will project require relocation of existing utilities? Unknown
5. Are there any required off-site improvements (or right-of-way dedications)? No
6. Is the site in a flood plane? No
7. Is the site in an airport impact zone? No
8. Does the site contain any underground storage tanks? No
9. Does the site contain any adverse soil conditions? No
10. Will the site require an environmental assessment? No
11. Will rezoning or a special use permit be required? No
12. Will any connection fees need to be paid? No
13. Will any water rights need to be deeded? No
14. Will construction traffic degrade existing access or facilities? Unknown
15. Will the site require any hazardous material abatement? Unknown
16. Other site considerations affecting cost? (describe): Unknown
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred? Unknown
(Programming is an architectural definition of the needs/problems that must be addressed by the project) Unknown
2. Has any advanced planning occurred in previous CIPs? No
3. Net Square footage required (including storage space)
New Construction SF:
Remodel/Renovation SF: 14720
Addition SF
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
5. Approximate quantity of staff to occupy facility: 85
6. Approximate number of visitors per day: 220
7. Will this project require funding for any furnishings, fixtures and equipment? Unknown
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): Yes
9. How many years of future growth will this project accommodate? 50
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project: Classroom, office space and conference rooms.
Submit Status Submit
 

You can also find documentation on ASP.NET at MSDN.