Submitted Application for a 2013 CIP Project

View all 2013 CIP Applications.              

AppID3226
I. Administrative Section 
Project Name: Belrose Building Fire Alarm System Upgrades
Project Description (One Sentence): Upgrades to the existing fire alarm system for the Belrose Building to meet current fire and ADA codes.
Project Location: County: Clark
Project Location: City: Las Vegas
Department (department requesting project): Administration
Division (division requesting project): Buildings & Grounds
Agency (agency requesting project): N/A
Agency contact person: Doug Hartwell
Contact phone: 702-486-4099
Contact email: dhartwell@admin.nv.gov
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 4
Has this project been previously requested in a prior CIP? Unknown
SPWD 4 digit Building No. (for existing buildings) 9831
Facility Condition Analysis Project No. (if recommended)
II. Narrative Section 
Project Justification (Essay)
Project Description: Upgrades to the existing fire alarm system for the Belrose Building to meet current fire and ADA codes.
Project Justification: This building is equipped with an automatic fire detection and alarm system, but the system is antiquated. It is recommended that the fire detection and alarm system be upgraded. When completed, the new system will provide visual, as well as audible notification, in accordance with ADA requirements.
Project Background Information: Buildings and Grounds fire contractor Siemens on Quarterly inspection on 2-21-2012 reported. PULL STATIONS WITH NOTE '1' HAVE NO GLASS BARS FOR TAMPER EVIDENCE. NEED REPLACEMENT. RECALL WAS NOT PROGRAMMED INTO ELEVATORS ON PROPERTY, THERE ARE MODULES THAT ARE INSTALLED BUT NOT WIRED. HORN STROBE APPLIANCE AT 2ND FLOOR HALLWAY BY VOCATIONAL TESTING NEEDS REPLACEMENT. EDWARDS MODEL 881D-AW WE FOUND NO HVAC SHUTDOWN THROUGH BUILDING AND A PAD 3 WHICH CONTROLS NOTIFICATION IN THE 628 TWO STORY BUILDING IS NOT LISTED FOR USE WITH THE EST QUICK START PANEL OR THE FIELD DEVICES IT CONTROLS (THIS PANEL NEEDS TO BE INDFEPENDENTLY RESET IN ORDER TO CLEAR AN ALARM UNACCEPTABLE). AUDIO COVERAGE THOUGHOUT BUILDING IS UNACCEPTABLE AND NEEDS TO BE ENGINEERED PER STATE N.R.S. SIEMENS STRONGLY RECOMMEDS TO CORRECT THESE ISSUES IMMEDIATELY. THIS REPORT WAS SENT TO THE BUILDING & GROUNDS DEPARTMENT It was also noted that: Siemens found many discrepancy on our inspection that are code violations which we at Siemens consider a public safety hazard. Currently the audio coverage is unacceptable as well as having no HVAC Shutdown on any these units. During our audio inspection most of your 2nd floor tenants could not hear the alarm going off. Siemens strongly recommends you to contact the State Fire Marshal and Building Department to get a solution to this issue.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced:
Year existing equipment was installed:
Manufacturer of existing equipment:
Model of existing equipment:
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? No
Ramifications if the Project is not Approved
(Short Essay): The buidling does not meet current fire codes and ADA codes associated with buidling fire safety. This condition would continue if this project is not completed.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): The buidling does not meet current fire codes and ADA codes associated with buidling fire safety. By completing this project, the building would be brought into compliance with current life-safety codes for building occupants and visitors.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? No
Explain:
Has any design work been completed on the proposed project? Unknown
What is the latest date this project could be completed without disrupting your program?
What is the driving proposed completion date?
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased):
2. Off-site construction cost:
3. On-site connection fees:
4. Utility connection fees:
5. Water rights deeded:
6. Furniture, Fixture and equipment costs:
7. Specialty equipment costs
8. Data and network equipment costs:
9. Telephone equipment costs:
10. Moving costs:
11. Costs for renovation of vacated space:
12. Costs for correction of known deficiencies:
(describe deficiencies)
13. Costs of any known commitments:
(describe commitments)
14. Costs of any hazardous material abatement:
(describe hazardous materials)
15. Total project costs:
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost:
a. Agency:
b. Federal
c. Other/Donor
d. State
(describe source of 'Other' funding):
Total:
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres)
2. Will this project require new parking spaces?
3. Are utilities available to site?
4. Will project require relocation of existing utilities?
5. Are there any required off-site improvements (or right-of-way dedications)?
6. Is the site in a flood plane?
7. Is the site in an airport impact zone?
8. Does the site contain any underground storage tanks?
9. Does the site contain any adverse soil conditions?
10. Will the site require an environmental assessment?
11. Will rezoning or a special use permit be required?
12. Will any connection fees need to be paid?
13. Will any water rights need to be deeded?
14. Will construction traffic degrade existing access or facilities?
15. Will the site require any hazardous material abatement?
16. Other site considerations affecting cost? (describe):
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
2. Has any advanced planning occurred in previous CIPs?
3. Net Square footage required (including storage space)
New Construction SF:
Remodel/Renovation SF:
Addition SF
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Select
5. Approximate quantity of staff to occupy facility:
6. Approximate number of visitors per day:
7. Will this project require funding for any furnishings, fixtures and equipment?
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks):
9. How many years of future growth will this project accommodate?
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:
Submit Status Submit
 

You can also find documentation on ASP.NET at MSDN.