Submitted Application for a 2013 CIP Project

View all 2013 CIP Applications.              

AppID3221
I. Administrative Section 
Project Name: Division of Forestry Tree Nursery Paving Project
Project Description (One Sentence): Pave access road and parking lot for nursery customers and staff, includes curb and gutter and ADA compliance issues.
Project Location: County: Clark
Project Location: City: N. Las Vegas
Department (department requesting project): CNR
Division (division requesting project): Forestry
Agency (agency requesting project): Select
Agency contact person: Amy Dunn
Contact phone: 702-486-5411
Contact email: LasVegasNursery@forestry.nv.gov
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). Statewide 13
Has this project been previously requested in a prior CIP? Yes
SPWD 4 digit Building No. (for existing buildings) 9966
Facility Condition Analysis Project No. (if recommended) 2010
II. Narrative Section 
Project Justification (Essay)
Project Description: Pave the access road and parking lot. The new, paved road would branch off of an existing paved road. The area to be paved includes a parking lot for employees and customers, a total of 16,600 sq ft. This paving project would also include 1,500 linear feet of curb and gutters.
Project Justification: This project is needed to alleviate dust hazards and continual degradation of the road surface during seasonal floods.
Project Background Information: This nursery has been in service for over twenty years. For the past four years the grading of this road has been impacted by seasonal flooding and limits access by employees and visitors. The small tractor that is used to regrade this surface has limited success in leveling and securing the road. Paved access and parking areas would also alleviate the dust hazard at this facility.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced:
Year existing equipment was installed:
Manufacturer of existing equipment:
Model of existing equipment:
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? Unknown
Ramifications if the Project is not Approved
(Short Essay): If this project isn’t approved, access will remain limited during seasonal washouts and the dust hazards will persist.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Currently, a dirt road provides access for employees and customers to the Las Vegas Nursery. The soil composition at this location has a high potential for erosion and water run off during spring floods and have resulted in gullies and washouts each spring. This not only impedes access but also impacts the ability to evenly grade the road surface. This dirt road and parking lot is the source of dust contamination and negatively impacts visitors, employees and equipment.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? No
Explain:
Has any design work been completed on the proposed project? Unknown
What is the latest date this project could be completed without disrupting your program? 06/30/2015
What is the driving proposed completion date?
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased): 0.0000
2. Off-site construction cost: 0.0000
3. On-site connection fees: 152911
4. Utility connection fees: 0.0000
5. Water rights deeded: 0.0000
6. Furniture, Fixture and equipment costs: 0.0000
7. Specialty equipment costs
8. Data and network equipment costs: 0.0000
9. Telephone equipment costs: 0.0000
10. Moving costs: 0.0000
11. Costs for renovation of vacated space: 0.0000
12. Costs for correction of known deficiencies: 0.0000
(describe deficiencies)
13. Costs of any known commitments: 0.0000
(describe commitments)
14. Costs of any hazardous material abatement: 0.0000
(describe hazardous materials)
15. Total project costs: 0.0000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost: 0.0000
a. Agency: 0.0000
b. Federal 0.0000
c. Other/Donor 0.0000
d. State 152911
(describe source of 'Other' funding):
Total: 152911
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres) 0
2. Will this project require new parking spaces? Yes
3. Are utilities available to site? Yes
4. Will project require relocation of existing utilities? Unknown
5. Are there any required off-site improvements (or right-of-way dedications)? Unknown
6. Is the site in a flood plane? Yes
7. Is the site in an airport impact zone? No
8. Does the site contain any underground storage tanks? No
9. Does the site contain any adverse soil conditions? Unknown
10. Will the site require an environmental assessment? Unknown
11. Will rezoning or a special use permit be required? No
12. Will any connection fees need to be paid? No
13. Will any water rights need to be deeded? No
14. Will construction traffic degrade existing access or facilities? Unknown
15. Will the site require any hazardous material abatement? No
16. Other site considerations affecting cost? (describe): Yes
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred? Unknown
(Programming is an architectural definition of the needs/problems that must be addressed by the project) Unknown
2. Has any advanced planning occurred in previous CIPs? No
3. Net Square footage required (including storage space)
New Construction SF: 16600
Remodel/Renovation SF: 0
Addition SF 0
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
5. Approximate quantity of staff to occupy facility: 20
6. Approximate number of visitors per day: 5
7. Will this project require funding for any furnishings, fixtures and equipment? Unknown
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): Yes
9. How many years of future growth will this project accommodate? 20
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:
Submit Status Submit
 