I. Administrative Section 
Project Name: Las Vegas Nursery ADA
Project Description (One Sentence): Replace existing cracked and crumbling sidewalks that are used by customers/public and staff.
Project Location: County: Clark
Project Location: City: N. Las Vegas
Department (department requesting project): CNR
Division (division requesting project): Forestry
Agency (agency requesting project): Select
Agency contact person: Amy Dunn
Contact phone: 702-486-5411
Contact email: LasVegasNursery@forestry.nv.gov
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). Statewide 10
Has this project been previously requested in a prior CIP? Yes
SPWD 4 digit Building No. (for existing buildings) 9966
Facility Condition Analysis Project No. (if recommended) 0283ADA1
II. Narrative Section 
Project Justification (Essay)
Project Description: Remove and replace 724 square feet of sidewalks at the Las Vegas Nursery.
Project Justification: The sidewalks to be removed and replaced are used daily by the public and employees and currently pose a tripping hazard and not compliant to ADA standards.
Project Background Information: This project was identified on January 30, 2002 during a Facility Condition Analysis review and was previously submitted as an ADA project last biennium.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced:
Year existing equipment was installed:
Manufacturer of existing equipment:
Model of existing equipment:
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? No
Ramifications if the Project is not Approved
(Short Essay): If the sidewalks at the nursery aren’t removed and replaced, tripping hazards will continue for customers and employees and ADA noncompliance.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): The sidewalks at the Las Vegas Nursery are deteriorated to the point they have created a potential tripping hazard and are in noncompliance with ADA standards. In order to meet the requirements of the ADA and ADAAG, an accessible path of travel should be provided for the public, employees and inmate crews. If this project is approved it will reduce the potential for trips and falls and meet ADA compliance.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? No
Explain:
Has any design work been completed on the proposed project? Unknown
What is the latest date this project could be completed without disrupting your program? 6/15/14
What is the driving proposed completion date? 6/30/14
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased): 0.0000
2. Off-site construction cost: 0.0000
3. On-site connection fees: 11115
4. Utility connection fees: 0.0000
5. Water rights deeded: 0.0000
6. Furniture, Fixture and equipment costs: 0.0000
7. Specialty equipment costs
8. Data and network equipment costs: 0.0000
9. Telephone equipment costs: 0.0000
10. Moving costs: 0.0000
11. Costs for renovation of vacated space: 0.0000
12. Costs for correction of known deficiencies: 0.0000
(describe deficiencies)
13. Costs of any known commitments: 0.0000
(describe commitments)
14. Costs of any hazardous material abatement: 0.0000
(describe hazardous materials)
15. Total project costs: 0.0000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost: 0.0000
a. Agency: 0.0000
b. Federal 0.0000
c. Other/Donor 0.0000
d. State 11115
(describe source of 'Other' funding):
Total: 11115
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres) 0
2. Will this project require new parking spaces? Yes
3. Are utilities available to site? Yes
4. Will project require relocation of existing utilities? No
5. Are there any required off-site improvements (or right-of-way dedications)? No
6. Is the site in a flood plane? No
7. Is the site in an airport impact zone? No
8. Does the site contain any underground storage tanks? No
9. Does the site contain any adverse soil conditions? Unknown
10. Will the site require an environmental assessment? Unknown
11. Will rezoning or a special use permit be required? No
12. Will any connection fees need to be paid? No
13. Will any water rights need to be deeded? No
14. Will construction traffic degrade existing access or facilities? Unknown
15. Will the site require any hazardous material abatement? No
16. Other site considerations affecting cost? (describe):
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred? No
(Programming is an architectural definition of the needs/problems that must be addressed by the project) No
2. Has any advanced planning occurred in previous CIPs? Unknown
3. Net Square footage required (including storage space)
New Construction SF: 724
Remodel/Renovation SF: 0
Addition SF 0
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
5. Approximate quantity of staff to occupy facility: 14
6. Approximate number of visitors per day: 5
7. Will this project require funding for any furnishings, fixtures and equipment? No
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): Unknown
9. How many years of future growth will this project accommodate? 20
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:
Submit Status Submit
 