Submitted Application for a 2013 CIP Project

View all 2013 CIP Applications.              

AppID3195
I. Administrative Section 
Project Name: Fire Sprinkler System Installation, Buildings 1 & 6
Project Description (One Sentence): This project would provide for a fire sprinkler sytem to be installed.
Project Location: County: Clark
Project Location: City: Las Vegas
Department (department requesting project): DHHS
Division (division requesting project): MH/DS
Agency (agency requesting project): SNAMHS
Agency contact person: Tom Clements
Contact phone: 702-498-7598
Contact email: tclements@snamhs.nv.gov
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project).
Has this project been previously requested in a prior CIP? Yes
SPWD 4 digit Building No. (for existing buildings) 1949, 1954
Facility Condition Analysis Project No. (if recommended) 1949SFT1, 1954SFT2
II. Narrative Section 
Project Justification (Essay)
Project Description: This project would provide for a fire sprinkler system to be installed including backflow prevention and monitoring.
Project Justification: Pursuant to the Nevada State Fire Marshal Regulation, NAC 477.915 (c) states, that every building owned or occupied by the state which is designated as a B occupancy, or has a floor area greater than 12,000 square feet on any floor or 24,000 square feet on all floors or is an R-1 occupancy, must have sprinklers installed when the building is remodeled or has an addition. Building 1 (SPWD 1949) is currently classified as a B occupancy, whereas Building 6 (SPWD 1954)
Project Background Information: This project or a portion thereof was previously recommended in the FCA report dated 6/25/1998. It has been amended accordingly to reflect conditions observed during the most recent survey date of 2/22/2007.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced:
Year existing equipment was installed:
Manufacturer of existing equipment:
Model of existing equipment:
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? Unknown
Ramifications if the Project is not Approved
(Short Essay): If the project is not approved, the building's occupants will be at risk from an uncontrollable fire.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): If the project is approved, the building will be brought up to safety compliance.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? Unknown
Explain:
Has any design work been completed on the proposed project? Unknown
What is the latest date this project could be completed without disrupting your program? 6/30/13
What is the driving proposed completion date?
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased): 0.0000
2. Off-site construction cost: 241763
3. On-site connection fees: 0.0000
4. Utility connection fees: 0.0000
5. Water rights deeded: 0.0000
6. Furniture, Fixture and equipment costs: 0.0000
7. Specialty equipment costs 0.0000
8. Data and network equipment costs: 0.0000
9. Telephone equipment costs: 0.0000
10. Moving costs: 0.0000
11. Costs for renovation of vacated space: 0.0000
12. Costs for correction of known deficiencies: 0.0000
(describe deficiencies)
13. Costs of any known commitments: 0.0000
(describe commitments)
14. Costs of any hazardous material abatement: 0.0000
(describe hazardous materials)
15. Total project costs: 0.0000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost: 0.0000
a. Agency: 0.0000
b. Federal 0.0000
c. Other/Donor 0.0000
d. State 0.0000
(describe source of 'Other' funding):
Total: 241763
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres) 0
2. Will this project require new parking spaces?
3. Are utilities available to site?
4. Will project require relocation of existing utilities?
5. Are there any required off-site improvements (or right-of-way dedications)?
6. Is the site in a flood plane?
7. Is the site in an airport impact zone?
8. Does the site contain any underground storage tanks?
9. Does the site contain any adverse soil conditions?
10. Will the site require an environmental assessment?
11. Will rezoning or a special use permit be required?
12. Will any connection fees need to be paid?
13. Will any water rights need to be deeded?
14. Will construction traffic degrade existing access or facilities?
15. Will the site require any hazardous material abatement?
16. Other site considerations affecting cost? (describe):
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred?
(Programming is an architectural definition of the needs/problems that must be addressed by the project)
2. Has any advanced planning occurred in previous CIPs?
3. Net Square footage required (including storage space)
New Construction SF: 0
Remodel/Renovation SF: 35300
Addition SF 0
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Business
5. Approximate quantity of staff to occupy facility: 70
6. Approximate number of visitors per day: 100
7. Will this project require funding for any furnishings, fixtures and equipment? Unknown
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): Unknown
9. How many years of future growth will this project accommodate? 10
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:
Submit Status Submit
 

You can also find documentation on ASP.NET at MSDN.