Project Name: Florence McClure Women's Correctional Center - Roof Replacment
Project Description (One Sentence): Replace the older portion of roofing.
Project Location: County: Clark
Project Location: City: N. Las Vegas
Department (department requesting project): Corrections
Division (division requesting project): So. Nevada Womens Correctional Facility
Agency (agency requesting project): N/A
Agency contact person: Kent LeFevre
Contact phone: 702.486.9928
Contact email: klefevre@doc.nv.gov
At the Department level ranking of this project:
The Department will rank their projects 1 through the lowest ranked project (i.e., If 5 projects were submitted by the Department a ranking of 1 would be assigned to the most important or most needed project and a ranking of 5 would be the least needed project). 3
Has this project been previously requested in a prior CIP?
SPWD 4 digit Building No. (for existing buildings) 9893
Facility Condition Analysis Project No. (if recommended) 2005
II. Narrative Section 
Project Justification (Essay)
Project Description: Scope of work: Replace the older portion of roofing. replace damaged insulation, crickets, curbs, etc. for a complete installation. Provide a 20 year min. warrantee.
Project Justification: Service of a certified roofing contractor is required to identify leak locations and make the appropriate repairs. SPWB has surveyed our roofing and agreed it does leak. Roofing survey was recommended in the Facility Condition Analysis printed in June, 2005. Roof replacement is recommended by SPWB. The cost is SPWB's estimate on the 2012 FMWCC Facility Condition Analysis Report. Requested FY 04-05, FY 08-09, FY 10-11, and FY 12-13.
Project Background Information: $50,000 repairs requested in FY 04-05 and FY 08-09 budgets.
Mechanical and/or Electrical Equipment Replacement Projects:
Type of equipment to be replaced:
Year existing equipment was installed:
Manufacturer of existing equipment:
Model of existing equipment:
Hazardous Materials (Asbestos, Lead Paint, etc.):
Will this project require any hazardous material abatement? Unknown
Ramifications if the Project is not Approved
(Short Essay): Leaks will continure to post a risk to State property, Inmates and Staff.
Health, Life Safety, and/or Legal Issues
Please describe any health, life safety, and/or legal issues that will be resolved by completing this project (Short Essay): Smoke alarm and light fixture damage has already occurred and will drastically escalate if repairs are not made. Leaks occur throughout the facility causing damage to the structure and equipment as well as creating a health and safey situation.
Proposed Project Schedule Impacts/Issues
1. Will this project require relocating personnel or vacating the building for any period of time? Unknown
Explain:
Has any design work been completed on the proposed project? No
What is the latest date this project could be completed without disrupting your program? 2014
What is the driving proposed completion date?
III. Cost Estimate Section 
Preliminary Cost Estimate and Funding Sources (The SPWD will prepare all final cost estimates. This schedule is for preliminary purposes only.)
1. Land Cost (if land must be purchased): 0.0000
2. Off-site construction cost: 0.0000
3. On-site connection fees: 0.0000
4. Utility connection fees: 0.0000
5. Water rights deeded: 0.0000
6. Furniture, Fixture and equipment costs: 0.0000
7. Specialty equipment costs
8. Data and network equipment costs:
9. Telephone equipment costs:
10. Moving costs:
11. Costs for renovation of vacated space:
12. Costs for correction of known deficiencies:
(describe deficiencies)
13. Costs of any known commitments:
(describe commitments)
14. Costs of any hazardous material abatement:
(describe hazardous materials)
15. Total project costs: 0.0000
NOTE: COSTS FOR EXTENDED LEASE AGREEMENTS MUST BE INCLUDED IN YOUR OPERATING BUDGET
16. Proposed funding of total project cost:
a. Agency:
b. Federal
c. Other/Donor
d. State 1706544
(describe source of 'Other' funding):
Total: 1706544
17. Agency point of contact for outisde funding if 16a, 16b, or 16c funding sources are providing funds.
a. Name
b. Phone Number
c. Email Address
IV. Analysis Section 
Site Analysis (New construction only)
1. Estimated land area to be acquired (acres) 0
2. Will this project require new parking spaces? No
3. Are utilities available to site? Yes
4. Will project require relocation of existing utilities? No
5. Are there any required off-site improvements (or right-of-way dedications)? No
6. Is the site in a flood plane? No
7. Is the site in an airport impact zone? No
8. Does the site contain any underground storage tanks? No
9. Does the site contain any adverse soil conditions? No
10. Will the site require an environmental assessment? No
11. Will rezoning or a special use permit be required? No
12. Will any connection fees need to be paid? No
13. Will any water rights need to be deeded? No
14. Will construction traffic degrade existing access or facilities? No
15. Will the site require any hazardous material abatement? No
16. Other site considerations affecting cost? (describe): No
V. Programming Section 
Programming (New construction, building remodels, and building additions only)
1. Has any architectural programming occurred? No
(Programming is an architectural definition of the needs/problems that must be addressed by the project) No
2. Has any advanced planning occurred in previous CIPs? No
3. Net Square footage required (including storage space)
New Construction SF:
Remodel/Renovation SF: 167156
Addition SF
Total project SF:
4. Occupancy type (Assembly, business, educational, factory/industrial, high hazard, institutional, mercantile, residential, storage, utility/miscellaneous) : Institutional
5. Approximate quantity of staff to occupy facility: 700
6. Approximate number of visitors per day: 30
7. Will this project require funding for any furnishings, fixtures and equipment? No
8. For existing facilities, are there any known hazardous materials? (i.e., Asbestos, lead paint or underground storage tanks): No
9. How many years of future growth will this project accommodate? 20
10. List of required facilites (laboratory space, classroom space, office space, conference rooms, cafeterias, maintenance shops, garages) and any unusual related equipment required for your project:
Submit Status Submit
 

You can also find documentation on ASP.NET at MSDN.