Application for Capital Improvement Project
2017-2018 Biennium


Weelcome to the State of Nevada using agency website to request capital improvement projects.
Below is the table of contents and the overall schedule

1.   INSTRUCTIONS

2.   Project Manager Assignments                                                                                         A.  2017 Board Recommendation

3.   Project Application Worksheet                                                                                         B.  2017 Governor's Recommendation

4 .  Project Application Submittal Form                                                                                  C. 2017 Governor's Recommendation XL

5.   Guidelines for Narrative

6.   View 2015 CIP Applications

7.   View 2013 CIP Applications

8.   15-CIP Approved Summary Report

9. 13-CIP Approved Summary Report

The schedule for the CIP process follows:

April 4, 2016 Applications due to the SPWD.

August 24 & 25, 2016 Agency presentations to the SPWB.

September, 2016 SPWD Administrator's presentation to the SPWB.

September 30, 2016 SPWB recommendations to Governor.

February, 2017 Legislative session begins.

If you have any questions, please contact the appropriate SPWD project manager (see appendix A) or Ward Patrick at (775) 684-4102.